It would
take >20 windfarms the size of Whitelee to generate the same amount of
intermittent electricity every year as the 24/7 electricity generated by
Hinkley [See links below]. But since windfarms only have an average lifespan of
22.5 years, compared with Hinkley’s 60 year design life, that’s equivalent to 54 Whitelee-sized windfarms.
----------------------------------------//----------------------------------------
Steel/All
Metals HPC
All site:
230,000 t Rebar + 2(70,903 t [All Metals]/1600 MW] = 371,806 t
Installed
Capacity: 3260 MW. Design Life: 60 years. Capacity Factor: 90%.
Electricity
generated: 1542.1 TWh
Steel
used per unit of electricity generated: 0.241 kg/MWh
Per Peterson – P.13: 1600 MW EPR, All Metals [tonnes]
EDF – Capacity Factor 90%. 60 year Design Life. 230,000 tonnes of rebar contract
EDF – Capacity Factor 90%. 60 year Design Life. 230,000 tonnes of rebar contract
Steel/All
Metals, Whitelee
Per
Turbine: 40 t Rebar + 320 t [Turbine} + 80 t [Nacelle] = 440 t
Total for 215 Turbines: 94,600 t
Total for 215 Turbines: 94,600 t
Installed
Capacity: 539 MW. Lifespan: 22.5 years. Capacity Factor: 27%
Electricity
generated: 28.7 TWh
Steel
used per unit of electricity generated: 3.296 kg/MWh
Per unit of electricity generated:
Wind Power uses 13.7X more Steel
[All Metals] than Nuclear Power.
[All Metals] than Nuclear Power.
----------------------------------------//----------------------------------------
Concrete,
HPC
All site:
3,000,000 t
Concrete
used per unit of electricity generated: 1.945 kg/MWh
Concrete,
Whitelee
All site:
Whitelee 120,000 t + Whitelee Extension 100,800 t = 220,800 t
Concrete
used per unit of electricity generated: 7.693 kg/MWh
Per unit of electricity generated:
Wind Power uses 4.0X more Concrete
than Nuclear Power.
----------------------------------------//----------------------------------------
54 such
windfarms would use 5,085,900 tonnes of steel/all metals.
That's an extra 4,714,000 tonnes of steel [all metals].
About Steel – Raw Materials:
That's an extra 4,714,000 tonnes of steel [all metals].
About Steel – Raw Materials:
20 GJ of
energy is 5.556 MWh of energy used for every tonne of steel produced. For the
extra 4,714,000 tonnes of steel needed, an extra 26 TWh of energy is required
[20 years of Whitelee Windfarm 22.5 years lifespan]. Then there’s the mining of
an extra 7,542,400 tonnes of iron ore and 3,629,800 tonnes of coal [770 kg
coal/600 kg coke]; this is shipped by 80 – 140,000 tonne bulk carriers.
----------------------------------------//----------------------------------------
54 such
windfarms would use 11,923.200 tonnes of concrete.
That’s an extra 8,923,200 tonnes of concrete.
That’s an extra 8,923,200 tonnes of concrete.
The extra
8,923,200 tonnes of concrete uses 1.583 TWh of energy [1¼ years of Whitelee’s
generation]. Coal use is 300,000 tonnes and CO2 emissions 1.018
million tonnes [1.77 years of Whitelee’s generation].
----------------------------------------//----------------------------------------
“…The CCC
has suggested that if the current block was lifted, 35GW of onshore wind could
be deployed by 2035 to help to meet the UK’s carbon reduction targets…”
35 GW Onshore wind by 2035
35 GW Onshore wind by 2035
----------------------------------------//----------------------------------------
35 GW of
Onshore Wind – That’s 65 Whitelee-sized Windfarms.
How much avoidable Waste of Steel?
How much avoidable Waste of Concrete?
How much avoidable Waste of Steel?
How much avoidable Waste of Concrete?
Time for
another Blog Post!
No comments:
Post a Comment